Order process and bulk lead time


Basically,every new customer who comes to us is very concerned about the bulk leadtime. After we gave the leadtime,some of them think this is too long and can’t accept it. So I think it is necessary to show up our production process and bulk leadtime on our website. It can help new customers to know the production process and understand why our production lead time needs so long.

Normally,we have two timeline that we can run off.The first timeline is using available fabric,this one is shorter. The second is using customise fabric,which will need one more month than using available fabric.

1.Timeline of using available fabric below for your reference:

Order process

Time

Discuss sample details and place the sample order

1 – 5 days

Proto samples production

15 – 30 days

Express delivery

7 – 15 days

Sample fitting and fabric testing

2 – 6 days

Order confirmed and paid the deposit

1 – 5 days

Fabric production

15 – 25 days

PP samples production

15 – 30 days

Express delivery

7 – 15 days

PP samples fitting and accessories confirming

2 – 6 days

Bulk production

30 – 45 days

Total bulk lead time

95 – 182 days

2.Timeline of using customise fabric below for your reference:

Order process

Time

Discuss sample details,place the sample order and supply the pantone code.

1 – 5 days

Lab dips

5 – 8 days

Proto samples production

15 – 30 days

Express delivery

7 – 15 days

Sample fitting and fabric testing

2 – 6 days

Order confirmed and paid the deposit

1 – 5 days

Fabric production

30 – 50 days

PP samples production

15 – 30 days

Express delivery

7 – 15 days

PP samples fitting and accessories confirming

2 – 6 days

Bulk production

30 – 45 days

Total bulk lead time

115 – 215 days

The above two timeline are for reference only,the accurate timeline will change based on style and quantity. Any questions please send the inquiry to us,we will reply to you in 24 hours.