Basically,every new customer who comes to us is very concerned about the bulk leadtime. After we gave the leadtime,some of them think this is too long and can’t accept it. So I think it is necessary to show up our production process and bulk leadtime on our website. It can help new customers to know the production process and understand why our production lead time needs so long.
Normally,we have two timeline that we can run off.The first timeline is using available fabric,this one is shorter. The second is using customise fabric,which will need one more month than using available fabric.
1.Timeline of using available fabric below for your reference:
Order process |
Time |
Discuss sample details and place the sample order |
1 – 5 days |
Proto samples production |
15 – 30 days |
Express delivery |
7 – 15 days |
Sample fitting and fabric testing |
2 – 6 days |
Order confirmed and paid the deposit |
1 – 5 days |
Fabric production |
15 – 25 days |
PP samples production |
15 – 30 days |
Express delivery |
7 – 15 days |
PP samples fitting and accessories confirming |
2 – 6 days |
Bulk production |
30 – 45 days |
Total bulk lead time |
95 – 182 days |
2.Timeline of using customise fabric below for your reference:
Order process |
Time |
Discuss sample details,place the sample order and supply the pantone code. |
1 – 5 days |
Lab dips |
5 – 8 days |
Proto samples production |
15 – 30 days |
Express delivery |
7 – 15 days |
Sample fitting and fabric testing |
2 – 6 days |
Order confirmed and paid the deposit |
1 – 5 days |
Fabric production |
30 – 50 days |
PP samples production |
15 – 30 days |
Express delivery |
7 – 15 days |
PP samples fitting and accessories confirming |
2 – 6 days |
Bulk production |
30 – 45 days |
Total bulk lead time |
115 – 215 days |
The above two timeline are for reference only,the accurate timeline will change based on style and quantity. Any questions please send the inquiry to us,we will reply to you in 24 hours.